Transportation of the upper block reactor cover for Kursk NPP-2
The "upper block reactor cover" for Kursk NPP-2 of the first power unit was transported from the territory of the Atommash plant to the construction site.
Due to the fact that transportation was carried out on public roads, a transport scheme was chosen using Goldhofer hydraulic modular axles. The trailer in this configuration has 15 axles with 8 wheels per axle, which allows you to distribute the load on the roadway and reduce the damage caused.
Maximum dimensions of the road train: 37.06 x 4.58 x 4.64 m, weight 168.98 t.