A set of measures for the delivery of equipment from the port of Haydarpasha to Volgodonsk for the EuroChem Group of companies.
As part of the project for the construction of a potash salt processing complex (KCI) of the EuroChem Group of companies, our company's specialists, as well as contractors involved, carried out a set of measures to deliver equipment from the port of Haydarpasa, Istanbul, to the temporary storage site in Volgodonsk.
Within the framework of this project, the following activities were carried out::
Transportation from the rear of the Haydarpasa port to the berth is organized;
Equipment was loaded onto Ro-Ro barges using crawler cranes with a lifting capacity of 300 and 600 tons;
Water transportation was carried out on the route Istanbul-Volgodonsk;
Transshipment from water to road transport was performed using gantry cranes with a lifting capacity of 630 tons each;
Car transportation was carried out from the berth to the temporary storage area. Transportation of heavy equipment was carried out using GOLDHOFER modular platforms of the THP/SL series in the configuration of 18 axles in one and a half lines;
The equipment was unloaded onto the curbstones due to the hydraulic suspension stroke of the modular platform.